What happens between an accepted ADU proposal and breaking ground?

Nov 13, 2026 | ADUs, How the build works

ADU site prep in Grand Junction with the building pad excavated, gravel base and orange safety fencing behind the main house

By Caleb Blair | God's Country Development

The period between an accepted ADU proposal and the first excavator arriving is easy to underestimate. From the outside, it can look like waiting. From the builder's side, it is when the project has to become a specific, coordinated construction package instead of a good idea and a price range.

At God's Country Development, that part of the work matters a great deal, because we aim to reach the construction agreement with detailed plans, known inclusions and minimal allowances.

First, what happens before the proposal?

Our process begins with a free, no-obligation discovery conversation. You might use Check My Lot, fill out our contact form or call with a property and an idea. We talk about what you're trying to achieve and whether an ADU looks capable of doing it.

Next comes our first on-site visit, which is also free and no-obligation. We look at room for the unit, access, utilities, grade, parking, privacy and other constraints. After that, we put together a turnkey proposal covering the proposed scope, expected timeline, general inclusions and next steps.

Accepting a proposal moves you into preconstruction. Preconstruction is real design and coordination work, and at GCD it isn't billed as a separate fee: design, revisions, permit materials and the build packet are covered within the construction contract's milestone-based payment schedule. If you finish design and decide not to sign the construction agreement, the only cost is the plan cost, about $200 to $400. When the project goes ahead, that cost is normally folded into the construction price. Whoever you hire, ask how preconstruction is paid for before that work begins.

What preconstruction is meant to accomplish

1. Design around the real use case

An investor building for a tenant may prioritize durability, a separate entry and efficient rentable space. A family building for an aging parent may prioritize a single-level route, bathroom access and long-term adaptability. The plan needs to fit the life that will happen inside the building.

We work through drawings and revisions with the owner, including how the ADU relates to the existing house. Exterior appearance, walking paths, parking and the privacy of both households belong in this stage.

In our experience, design typically takes anywhere from about two days, when we're adapting a stock plan, to about two months for a fully original design with several rounds of revisions. Those are typical ranges, not promised plan-delivery dates. Timely owner decisions make a real difference.

2. Find the details that can change the project

What does the utility route look like? What is the foundation design based on? Is a proposed window in the wrong place for privacy? Are all the selections and material standards actually written down? These are the questions worth resolving before trades are booked.

Our preconstruction includes coordinating with our subcontractors to uncover scope gaps, construction conflicts and site-specific problems. We want a build packet full of real decisions, not a stack of missing assumptions.

3. Prepare the approval and permit package

The documents vary by jurisdiction and project. They may include planning materials, structural drawings, truss and floor information, energy and mechanical load calculations where required, electrical utility paperwork, and any other local clearance the building department asks for.

Jurisdiction sets the order. Inside the City of Grand Junction, an ADU needs a Planning Clearance before the building permit, and the City requires a licensed general contractor to build it. In unincorporated Mesa County, the county's ADU guide calls for planning approval before the building permit is submitted, and where septic applies, it must be verified during plan review. Our Mesa County ADU permits guide walks through the city-versus-county steps.

A planning submission is not the same thing as an issued building permit, and a builder should never promise that the government or a utility will meet a particular review date.

4. Agree on the construction scope

Preconstruction ends with completed plans, a detailed scope and build packet, and a signed construction agreement. Our approach is a fixed price with minimal allowances, with assumptions and any later changes documented in writing.

What the homeowner should expect to review

Item What you should understand
Floor and site plans Room uses, entry and parking, building placement
Finishes and systems Included products or clear selection standards
Utility approach Known work, unverified work and who is responsible
Scope and exclusions Exactly what the price does and does not cover
Allowances Which items are still allowances, and the amounts
Schedule Target construction duration and outside dependencies
Change process How owner choices or changed conditions affect cost and time

Ask questions until you understand the package. It is your property and your money.

Then construction starts

Once the required clearances and the construction agreement are in place, we move into the build. Construction generally takes about three to five months (roughly 90 to 115 working days) once permits are issued, and it can run longer because of utility service, inspections, owner changes or site conditions. We keep owners updated as the work progresses and deal with issues as they come up.